A 10Mt/a Refining Plant Inaugurated at Guangxi Petrochemical

abarrelfullabarrelfull wrote on 28 Mar 2013 12:20
Tags:

Latest News

{"module":"feed\/FeedModule","params":{"src":"http:\/\/killajoules.wikidot.com\/feed\/pages\/pagename\/blog%3A_start\/category\/blog\/limit\/10\/t\/My+Blog","limit":"4","module_body":"* %%linked_title%%"}}
  • Want a weekly review of refining news?

The inauguration ceremony of a 10Mt/a refining plant at PetroChina Guangxi Petrochemical was held in the Qinzhou city of Guangxi Zhuang Autonomous Region, on September 8, 2010.

The refining plant will annually supply 8.3 million metric tons of gasoline, diesel, aviation kerosene, and LPG, and 900,000 metric tons of polypropylene, aromatics, benzene, toluene, xylene mixed, and other petrochemical products to southwestern China, where the booming economy is swelling the energy demand.

By employing advanced and environmentally friendly full hydrogenation process, Guangxi Petrochemical produces all its oil products in compliance with the Euro-3 standard and 70% of them in compliance with the Euro-4 standard. In addition to a 3-level prevention and control system against environmental hazards and water pollution, the company has tightened its wastewater discharge standard from State Class 2 to 1, indicating a drop of petroleum pollutants from 10mg/l to 5mg/l, COD from 120mg/l to 60mg/l, and oxynitrides from 50mg/l to 15mg/l in discharged wastewater.

More than 70% of the wastewater can be recycled at Guangxi Petrochemical, thanks to an investment of RMB 50 million for minimal wastewater discharge. The remaining wastewater is collected and discharged through pressurized pipes rather than ducts, which may result in spillage when the drainage is blocked in rain.

According to the budget, Guangxi Petrochemical has invested RMB 1 billion, or 7% of its total investment in the project, in environmental protection.

Milestones

  • December 6, 2008 – The 100kt/a crude dock was completed.
  • December 13, 2008 – The 10Mt/a atmospheric-vacuum distillation unit and its auxillary facilities were completed.
  • November 14, 2009 – The 3.5Mt/a catalytic heavy oil cracking unit was capped.
  • February 5, 2010 – The tank farm of refined products was completed and delivered for operation.
  • February 27, 2010 – The 2.2Mt/a continuous reforming unit, 200kt/a polypropylene unit, and 40kscm/h hydrogen production unit were completed and delivered for operation.