BG Group Delivers First Gas from Scarab Saffron fields in Egypt

abarrelfullabarrelfull wrote on 06 May 2014 13:39
Tags:

Latest News

{"module":"feed\/FeedModule","params":{"src":"http:\/\/killajoules.wikidot.com\/feed\/pages\/pagename\/blog%3A_start\/category\/blog\/limit\/10\/t\/My+Blog","limit":"4","module_body":"* %%linked_title%%"}}
  • Want a weekly review of refining news?

29 March, 2003

BG Group plc and its partners announced today the delivery of first gas from the Scarab Saffron fields to the Egyptian domestic market on 29 March, 2003. The Scarab Saffron development is in the BG-operated West Delta Deep Marine (WDDM) Concession, offshore the Nile Delta, and is a central part of BG's rapidly developing gas business in Egypt.

Scarab Saffron, located 120 kilometres north of Alexandria, is the largest gas field development in Egypt. Situated in deeper water than any previous development in Egypt or the Mediterranean region, it is also the first sub-sea completion in the region, and has one of the longest tie-backs in the world.

Frank Chapman, Chief Executive, BG Group plc, said: “The delivery of first gas from Scarab Saffron is a major milestone for both BG Group and Egypt. We aim to be the premier gas operator in Egypt by 2006 when 40 per cent of total domestic production is expected to come from fields we operate. Scarab Saffron is another step forward towards achieving this aim.”

The development includes an offshore gathering network consisting of two pipelines – 36-inch and 24-inch - which are capable of supporting both Scarab Saffron and which has sufficient gas to supply two 3.6 million tonnes per annum (mtpa) trains of Egyptian LNG. Production is expected to reach a rate of 330 million standard cubic feet of gas per day (mmscfd), during a 90-day run-in period. This represents the minimum take or pay level of 75 per cent of the initial Daily Contracted Quantity (DCQ). During the run-in period the plant may be shut down periodically for start-up modifications.

The offshore facilities form the backbone for the development of the Simian Sienna fields for the initial supply of Egyptian LNG Train 1 and the proposed development of the Sapphire field for initial supply of the second train. Train 1 production is scheduled for the third quarter of 2005 with Train 2 due to follow in mid-2006.

Since 1997, BG has drilled 16 exploration and appraisal wells in the WDDM Concession, realising a 100 per cent success rate. In 1999, a Gas Sales Agreement (GSA) was signed with the Egyptian General Petroleum Corporation (EGPC) for the sale of gas into the domestic market. In December 2002 an agreement was signed to increase the DCQ set out in the GSA.

Under the amended GSA, the initial DCQ of 440 mmscfd rises in stages to a maximum of 633 mmscfd, three months after the first shipment of liquefied natural gas (LNG) from Egyptian LNG Train 1.
The Saurus, Serpent and Sequoia fields are intended to be developed at a later stage to supplement supplies to the first two LNG trains.

Notes to Editors
West Delta Deep Marine Concession
BG Group has a 50 per cent working interest in WDDM and Edison International holds the remaining 50 per cent. The partners were awarded the concession in 1995.
Burullus Gas Company, a joint venture company, formed by BG, Edison and EGPC, undertakes exploration, field development and operations on behalf of the WDDM concession holders.
The Scarab Saffron development consists of eight sub-sea wells, located in a water depth of about 700 metres, tied into a pipeline end manifold that is in turn tied back to an onshore terminal by two gas pipelines. Additional pipeline capacity has been installed to allow subsequent field developments to tie into the Scarab Saffron facilities. Field operations are controlled from the onshore terminal via electrical and hydraulic umbilical lines.
Under the amended GSA the DCQ rates are:

  • Up until the end of 2003 440 mmscfd
  • From January 1, 2004 586 mmscfd
  • From January 1, 2005 626 mmscfd
  • From January 1, 2006 533 mmscfd

A further rise of 100 mmscfd is intended to take effect three months after the first shipment from Egyptian LNG occurs and this DCQ will stay in place for seven years.

In April 2001, BG and Edison signed a fully termed agreement with EGPC setting the commercial foundation for Egyptian LNG making the partners the first and currently only upstream players in Egypt with a definitive export agreement allowing the export of gas from a development within a concession area. Train 1 construction is under way and project financing has been mandated. An early works programme for Train 2 consisting of detailed engineering, procurement of long lead-time items and site preparation work began in December 2002.

BG Group in Egypt

  • BG Group has been active in Egypt since 1989 and by 2007 is expected to have invested some US$1.2 billion in the Egyptian energy sector.
  • BG is the operator of the offshore Rosetta Concession, which came on-stream in January 2001 and delivers gas into the Egyptian national grid under a 25-year agreement.
  • BG and partners are developing the US$1.9 billion Egyptian LNG export project at Idku, east of Alexandria. Output from a 3.6 mtpa first train has been sold to Gaz de France for a 20-year period and a second train of the same size is in an advanced stage of marketing.
  • In addition, BG is a 37.5 per cent shareholder in the Nile Valley Gas Company, a gas distribution company, which delivers natural gas to industrial and residential customers in the Upper Egypt area.

Partners

  • Egyptian General Petroleum Corporation and Egyptian Natural Gas Holding Company (EGAS) are the state-owned corporations that plan, implement and oversee policies relating to the oil and gas sector in Egypt. They co-ordinate these activities through their participation in companies involved in exploration, production, refining, processing, petrochemicals, distribution and transportation.
  • Edison International S.p.A., Italy's leading private energy group, is a partner in Rosetta, WDDM, Egyptian LNG and in the Nile Valley Gas Company.

Related News

{"module":"feed\/FeedModule","params":{"src":"http:\/\/killajoules.wikidot.com\/feed\/pages\/pagename\/blog%3A_start\/tag\/upstream\/category\/blog\/limit\/10\/t\/My+Blog","limit":"3","module_body":"* %%linked_title%%"}}

Looking for information on the E&P sector?


Unless otherwise stated, the content of this page is licensed under Creative Commons Attribution-ShareAlike 3.0 License