Chevron To Start Surfactant Injection Try Out

abarrelfullabarrelfull wrote on 04 Jul 2012 11:49
Tags:


September 11, 2008

Chevron Pacific Indonesia will start a try out in surfactant injection in Minas field. Drilling will start in October 2008, BPMIGAS Vice Chairman Abdul Muin said at a hearing with the parliament”s Commission VII in Jakarta on Tuesday (9/9).

“The Minas Surfactant try out will begin with a field trial by drilling one development well and 15 injection wells as well as building the facilities for injection and production,” Muin said.

Chevron will start building the facilities in end 2008 and is expected to be completed by 2011, he said. The chemical injection can be conducted in early 2012 at the earliest with a peak output of about 850 barrels a day. ***