September 2 reporter learned from North China Petrochemical Corporation, Huabei Petrochemical million tons refinery upgrading the quality and safety and environmental protection technological transformation project feasibility study report has been obtained the National Development and Reform Commission officially approved , the project entered the start-up phase.

This project was included in the national petrochemical industry restructuring and revitalization plan "ten key support for the project and the economic and social development in Hebei Province" Eleventh Five-Year Plan "key project. The project was basically completed in October 2012 and full production in December. By then, the 14 year refinery processing scale and capacity of enterprises with more than 10 million tons, Cangzhou Chemical City construction not only provide an important chemical raw materials, and will also provide a year in Beijing and Tianjin and North China market supply up to 800 million tons can reach Beijing Ⅳ standard of refined oil products and high-quality petrochemical products.

Huabei Petrochemical current annual refining capacity of 5.0 million tons. Affected by the oil processing capacity, for a long time, this company with high efficiency and high competitiveness as the goal of the road of the development of strategic industries struggling. Coupled with the implementation of the 500 million tons refinery technological innovation, the company limited by domestic equipment manufacturing and technical level, and the scientific and technological content below international standards. While companies pay close attention to technical innovation, optimize processes Beijing Ⅳ gasoline and diesel to produce high quality products, but some indicators of the refining device package of safety, environmental protection and energy saving significantly behind in advanced enterprises.

Huabei Petrochemical million tons refinery upgrading the quality and safety and environmental protection technological transformation projects as an opportunity to enhance the quality levels, changing patterns of development. Promote enterprise "science, green and sustainable development," the guiding ideology is the upgrading. Company only this feasibility study on upgrading lasted three years, the feasibility report to modify 16 times, the EIA report modify 8.

The upgrading program approved by the National Development and Reform Commission, for the 13.79% of the total investment of environmental protection investment in this project. Which will be new sets of main production unit, three sets of transformation devices and related systems supporting facilities are used the full hydrogenation fuel type process. This process has the international advanced level, to be able to meet the relevant requirements of environmental protection. In addition, due to the upgrading process using state-of-the-art technology of a large number of international oil refining, the transformation was complete, the full set of devices each year will reduce regional sulfur dioxide emissions by 78.5% per unit GDP carbon dioxide emissions 70 percent lower than in 2005.

The Renqiu by machine of this renovation project, Daxing supporting industries, the investment by the city government in the construction of 1.2 million kilowatts of thermal power plants and municipal sewage treatment plant project surfaced. 1.2 million kilowatts thermal power plants need some hot steam from the upgrading of refineries, refinery and 1.2 million kilowatts of thermal power plants add water, in the water from the treatment of municipal sewage treatment plant. Preliminary calculations, the two supporting completion of the project, Renqiu will disable more than 210 small heaters, the annual savings of 586,700 tons of standard coal, the annual savings of 1.1 million tons of fresh water will close more than 50 polluting enterprises, regional sulfur dioxide emissions of 7910 tons and 6224 tons of dust emission reduction of carbon dioxide emissions of 194 tons, 1.15 million tons of sewage emissions and increase the effectiveness of 322 million yuan.

Currently, Huabei Petrochemical with an annual output of 100 tons of ethylene and other large chemical project into the preparatory stage, upon completion, will produce large amounts of imported ethylene derivatives alternatives.