Technip awarded pipes and subsea structures installation contract for the Shenzi field

abarrelfullabarrelfull wrote on 03 Aug 2012 21:24
Tags:

Latest News

{"module":"feed\/FeedModule","params":{"src":"http:\/\/killajoules.wikidot.com\/feed\/pages\/pagename\/blog%3A_start\/category\/blog\/limit\/10\/t\/My+Blog","limit":"4","module_body":"* %%linked_title%%"}}
  • Want a weekly review of refining news?

February 27, 2007

Technip has been awarded a contract by BHP Billiton for the flowlines, risers and subsea structures installation for the development of the Shenzi field. This field is located in the Green Canyon area of the Gulf of Mexico in 4,300 feet of water depths. The Shenzi development requires delivery of a subsea system in water depths where Technip has extensive experience.

The contract covers the engineering, fabrication and installation of a system of two infield flowlines and six flowlines welded to steel catenary risers and connecting three drill centers to the production platform.

Pipeline end terminations (PLET) design is currently underway at Technip’s operations and engineering center in Houston (Texas) with PLET fabrication scheduled for Q3 and Q4 2007.

The flowlines and risers will be welded onshore, at Technip's spoolbase located in Mobile (Alabama), minimizing the duration of offshore operations.

Offshore installation will be carried out in Q1 2008 by the Deep Blue, Technip’s deepwater pipelay vessel. The Deep Blue will use the reel lay process, reducing the vessel’s required time in the field, thus limiting its exposure to weather and currents.

The Shenzi field is operated by BHP Billiton and owned by BHP Billiton (44%), Repsol (28%) and Hess (28%).