Tangshan LNG Tank 3 Roof Installed

abarrelfullabarrelfull wrote on 27 Jun 2012 08:27
Tags: asia china lng

Latest News

{"module":"feed\/FeedModule","params":{"src":"http:\/\/killajoules.wikidot.com\/feed\/pages\/pagename\/blog%3A_start\/category\/blog\/limit\/10\/t\/My+Blog","limit":"3","module_body":"* %%linked_title%%"}}
  • Want a weekly review of refining news?

HQCEC the EPC contractor of Tangshan LNG terminal 160,000 m3 tank successfully air lifting within the tank to install a comprehensive start.

L gas cap is the use of micro-pressure air lift, the use of high-power air blower into the compressed air to the tank, buoyancy, and the ground prefabricated good weighing 728 tons, 82 m diameter LNG storage tank dome rose to 36.5 m height. This helps to reduce high-altitude operations, reduce security risks, accelerate the construction schedule.

Priorities and difficulties in the construction of LNG storage tank or roof in the process of balancing and pressure to master the scientific and effective solution to seal, mutual coordination and cooperation between the blast and balance. In this regard, the six construction company has independently developed national utility model patents.

Tangshan LNG terminal following Jiangsu and Dalian LNG terminal and then an independent design, independent acquisition, self-construction and autonomy drive large-scale LNG project. On November 15 last year, on the 24th, six construction companies to complete the 1st and the 2nd tank or roof. At present, six construction companies realized a total 1.25 million safe working hours welding a passing rate of 98.3%.

Tangshan LNG terminal planning an LNG terminal and dedicated LNG ship unloading terminal and supporting facilities, the annual production of 3.5 million tons. The second phase project to build a 160,000 m3 LNG storage tanks, the annual production capacity of 6.5 million tons, and forward for 10 million tons a year.

Tangshan LNG terminal to receive liquefied natural gas resources from countries such as Australia and Qatar, the gas mainline and Yong Tang Qin (Langfang yongqing - Tangshan - Qinhuangdao) gas pipeline network is connected.

Tangshan LNG Terminal project in 2013 put into operation. After the completion of the project will be in North China to increase the reliable supply a new gas source to supplement the natural gas needs of Beijing, Tianjin, Tianjin and Hebei Tangshan and Qinhuangdao to meet seasonal demand for natural gas peaking.


Unless otherwise stated, the content of this page is licensed under Creative Commons Attribution-ShareAlike 3.0 License