Valero 1Q & 2Q Turnaround Schedule Update

abarrelfullabarrelfull wrote on 27 Jan 2011 06:39
Tags: refinery usa valero

Latest News

{"module":"feed\/FeedModule","params":{"src":"http:\/\/killajoules.wikidot.com\/feed\/pages\/pagename\/blog%3A_start\/category\/blog\/limit\/10\/t\/My+Blog","limit":"3","module_body":"* %%linked_title%%"}}
  • Want a weekly review of refining news?

Valero has updated its maintenance turnaround schedule. This list includes only major projects that will have a material impact on production, and it is subject to change. While we provide general guidance on the start and duration of the maintenance, we do not disclose specific beginning and end dates.
Refinery Unit BPD Month Days
Benicia Plantwide 170,000 Jan 42
Port Arthur Crude/Coker 100,000 Feb 51
Houston Crude 90,000 Feb 24
St. Charles MSCC/Alky 100,000 March 56
Ardmore Plantwide 90,000 March 37
McKee HCU 30,000 April 24