Concept selection for the Johan Sverdrup field early in 2014

abarrelfullabarrelfull wrote on 26 Dec 2013 15:02
Tags: europe lundin maersk norway statoil upstream

Latest News

{"module":"feed\/FeedModule","params":{"src":"http:\/\/killajoules.wikidot.com\/feed\/pages\/pagename\/blog%3A_start\/category\/blog\/limit\/10\/t\/My+Blog","limit":"3","module_body":"* %%linked_title%%"}}
  • Want a weekly review of refining news?

Statoil ASA (OSE:STL, NYSE:STO) and the partners in the Johan Sverdrup field in the North Sea continue their work to evaluate and optimise the field development concept. The final decision regarding concept selection will be made early in 2014.

At the same time, the partnership is working to award a contract for front-end engineering and design – FEED.

“We need to make the final clarifications and give the individual companies the opportunity to make a proper consideration. At the same time, the partners agree that we should award the FEED contract at soon as possible in order to keep momentum,” says Øivind Reinertsen, senior vice president for the Johan Sverdrup field.

The plan is to have the plan for development and operation (PDO)approved during the Norwegian Parliament’s (Stortinget) spring session of 2015. Production start-up is expected at the end of 2019.

The resource estimate for the field is between 1.8 – 2.9 billion barrels of oil equivalent.

Facts about the Johan Sverdrup field (PL 265, PL 501 and PL502)

• Johan Sverdrup is an oil field.
• Johan Sverdrup consists of a combined discovery which makes up one field.
• Location: Utsira High in the North Sea, 140 kilometres west from Stavanger.
• The water depth is 110 metres, and the reservoir depth is 1,900 metres.
• We expect approval of the plan for development and operation (PDO) during the Norwegian Parliament’s (Stortinget) spring session in 2015.
• Production start is expected at the end of 2019.
• The field has a production horizon until 2050.
• As part of the design basis it was decided early in 2013 that the field will be developed in phases. The first phase is the establishment of a field centre consisting of four platforms.
• It is recommended to transport the oil via pipeline to the Mongstad terminal in Hordaland, and to transport the gas to Statpipe and then further to the Kårstø processing plant in northern Rogaland.
• The field will receive power from land.

Partners:

PL 501: Lundin Norway (operator - 40%), Statoil (40%), Maersk Oil (20%)
PL 265: Statoil (operator - 40%), Petoro (30%), Det norske oljeselskap (20%), Lundin Norway (10%)
PL 502: Statoil (operator – 44.44%), Petoro (33.33%), Det norske oljeselskap (22.22%)


Related News

{"module":"feed\/FeedModule","params":{"src":"http:\/\/killajoules.wikidot.com\/feed\/pages\/pagename\/blog%3A_start\/tag\/upstream\/category\/blog\/limit\/10\/t\/My+Blog","limit":"3","module_body":"* %%linked_title%%"}}

Looking for information on the E&P sector?


Unless otherwise stated, the content of this page is licensed under Creative Commons Attribution-ShareAlike 3.0 License